Measure 4881

# of water control structures repaired/replaced

Requiredoutput

Tier 1: Collect today

A DRGR count entered from the grantee’s own project records.

Instrument
DRGR (Disaster Recovery Grant Reporting System), CDBG-DR Performance by Activity
Target
No target rule stated
Source document, column J 'Activity Measure Type', first at sheet row 16246

Grantee precedent for this measure

230 paired precedent measures, first 8 shown, closest first. Pairing basis is shown on each.

# of water control structures repaired/replaced [Total]

CDBG-DR 2013 National Disaster Resilience, HUD CDBG-DR performance by activity (DRGR)

Paired by name_equal. 2 rows in the source.

Attainment (result ÷ promised) by kind of promised value
Promised value isResultsGranteesPeriodsMedianMiddle halfAt or above target
goal revised after the fact2110%0% to 0%0%
0%target200%+

Example rows (results with a target first)

2 shown

  • West Tennessee River Basin Authority · as of 2026-10-20

    1 → 0 (0% of target) · count

    Source document
  • West Tennessee River Basin Authority · as of 2026-10-20

    1 → 0 (0% of target) · count

    Source document
Example rows (results with a target first), 2 shown
GranteePeriodPromisedActualUnit% of targetSource
West Tennessee River Basin Authorityas of 2026-10-2010count0%document
West Tennessee River Basin Authorityas of 2026-10-2010count0%document

# of pump stations repaired/replaced [Total]

CDBG-DR 2013 National Disaster Resilience, HUD CDBG-DR performance by activity (DRGR)

Paired by name_equal. 1 rows in the source.

Attainment (result ÷ promised) by kind of promised value
Promised value isResultsGranteesPeriodsMedianMiddle halfAt or above target
goal revised after the fact111167%167% to 167%100%
0%target200%+

Example rows (results with a target first)

1 shown

  • Town of Henning · as of 2026-10-20

    3 → 5 (167% of target) · count

    Source document
Example rows (results with a target first), 1 shown
GranteePeriodPromisedActualUnit% of targetSource
Town of Henningas of 2026-10-2035count167%document

# of linear feet of water/sewer line repaired/replaced [Total]

CDBG-DR 2013 National Disaster Resilience, HUD CDBG-DR performance by activity (DRGR)

Paired by name_equal. 3 rows in the source.

Attainment (result ÷ promised) by kind of promised value
Promised value isResultsGranteesPeriodsMedianMiddle halfAt or above target
goal revised after the fact331625%344% to 1,134%67%
0%target200%+

Example rows (results with a target first)

3 shown

  • City of Dyersburg · as of 2026-10-20

    8600 → 53789 (625% of target) · count

    Source document
  • Jackson Energy Authority · as of 2026-10-20

    2500 → 41056 (1,642% of target) · count

    Source document
  • Town of Henning · as of 2026-10-20

    10000 → 6266 (63% of target) · count

    Source document
Example rows (results with a target first), 3 shown
GranteePeriodPromisedActualUnit% of targetSource
City of Dyersburgas of 2026-10-20860053789count625%document
Jackson Energy Authorityas of 2026-10-20250041056count1,642%document
Town of Henningas of 2026-10-20100006266count63%document

# of manhole covers replaced [Total]

CDBG-DR 2013 National Disaster Resilience, HUD CDBG-DR performance by activity (DRGR)

Paired by name_equal. 2 rows in the source.

Attainment (result ÷ promised) by kind of promised value
Promised value isResultsGranteesPeriodsMedianMiddle halfAt or above target
goal revised after the fact221308%261% to 354%100%
0%target200%+

Example rows (results with a target first)

2 shown

  • City of Dyersburg · as of 2026-10-20

    50 → 200 (400% of target) · count

    Source document
  • Town of Henning · as of 2026-10-20

    40 → 86 (215% of target) · count

    Source document
Example rows (results with a target first), 2 shown
GranteePeriodPromisedActualUnit% of targetSource
City of Dyersburgas of 2026-10-2050200count400%document
Town of Henningas of 2026-10-204086count215%document

# of acres green infrastructure created [Total]

CDBG-DR 2013 National Disaster Resilience, HUD CDBG-DR performance by activity (DRGR)

Paired by name_equal. 1 rows in the source.

Attainment (result ÷ promised) by kind of promised value
Promised value isResultsGranteesPeriodsMedianMiddle halfAt or above target
goal revised after the fact1110%0% to 0%0%
0%target200%+

Example rows (results with a target first)

1 shown

  • STATE OF CONNECTICUT · as of 2026-10-20

    1 → 0 (0% of target) · count

    Source document
Example rows (results with a target first), 1 shown
GranteePeriodPromisedActualUnit% of targetSource
STATE OF CONNECTICUTas of 2026-10-2010count0%document

# of linear of sewer/water line constructed [Total]

CDBG-DR 2013 National Disaster Resilience, HUD CDBG-DR performance by activity (DRGR)

Paired by name_equal. 1 rows in the source.

Attainment (result ÷ promised) by kind of promised value
Promised value isResultsGranteesPeriodsMedianMiddle halfAt or above target
goal revised after the fact111183%183% to 183%100%
0%target200%+

Example rows (results with a target first)

1 shown

  • Jackson Energy Authority · as of 2026-10-20

    6800 → 12440 (183% of target) · count

    Source document
Example rows (results with a target first), 1 shown
GranteePeriodPromisedActualUnit% of targetSource
Jackson Energy Authorityas of 2026-10-20680012440count183%document

# of new structures built to 3 ft. freeboard [Total]

CDBG-DR 2013 National Disaster Resilience, HUD CDBG-DR performance by activity (DRGR)

Paired by name_equal. 1 rows in the source.

Attainment (result ÷ promised) by kind of promised value
Promised value isResultsGranteesPeriodsMedianMiddle halfAt or above target
goal revised after the fact1115%5% to 5%0%
0%target200%+

Example rows (results with a target first)

1 shown

Example rows (results with a target first), 1 shown
GranteePeriodPromisedActualUnit% of targetSource
Norfolkas of 2026-10-20201count5%document

# of small water retention devices/systems installed [Total]

CDBG-DR 2013 National Disaster Resilience, HUD CDBG-DR performance by activity (DRGR)

Paired by name_equal. 1 rows in the source.

Attainment (result ÷ promised) by kind of promised value
Promised value isResultsGranteesPeriodsMedianMiddle halfAt or above target
goal revised after the fact1110%0% to 0%0%
0%target200%+

Example rows (results with a target first)

1 shown

Example rows (results with a target first), 1 shown
GranteePeriodPromisedActualUnit% of targetSource
Norfolkas of 2026-10-20100count0%document